-
HSW CEUs
- The PASS Program is now eligible for the AIA Continuing Education program’s Health, Safety, and Welfare Units. Both the TI and NC portions of the program are worth 3 units each. Share this:Email[...]
The PASS Program is now eligible for the AIA Continuing Education program’s Health, Safety, and Welfare Units. Both the TI and NC portions of the program are worth 3 units each.
-
PASS Training Webinars: September 25-26th; October 3-4th
- See attached flyer for information Share this:EmailFacebookTwitter
See attached flyer for information
-
PASS in action: Share your experiences
- From: Helmer, Mike Sent: Thursday, March 15, 2018 9:18 AM To: Mike Malinowski Subject: RE: PASS (Prequalified Architectural Submittal System) Project Hello Mike, Here’s the update I promised for this[...]
From: Helmer, Mike
Sent: Thursday, March 15, 2018 9:18 AM
To: Mike Malinowski
Subject: RE: PASS (Prequalified Architectural Submittal System) ProjectHello Mike,
Here’s the update I promised for this PASS project.
The second review when very smooth and resulted with one remaining item requested by the City on March 8, 2018. Evidently there was a little confusion with our suggested format for the Green Code Checklist. Plan sheets that included the revised checklists were resubmitted to the City on March 14, 2018 and approved for issuance the same day.
All in all, the project was submitted on January 17, 2018 and ready to issue on March 14, 2018. That’s a total of 38 business days. The plans were under City review for less than 14 of those days.
I would say both parties performed well on this one.
Thanks,
Michael T. Helmer
Senior Building Plans Examiner
Development Services DepartmentBuilding Division
Working together to build a quality community.
Civic Center | 311 Vernon Street | Roseville, CA | 95678From: Helmer, Mike
Sent: Thursday, February 08, 2018 7:32 AM
Subject: RE: PASS (Prequalified Architectural Submittal System) ProjectMike,
This project, like many Kaiser projects, was highly detailed. The first review was started 3 business days after its submittal and took 6 business days to complete. Remember, the City has combination plans examiners, who review each project for all disciplines.
Our plans examiner reports that the design documents met the standards expected for a PASS project, which resulted in a marked reduction in the number of plan review comments likely for a project of this level.
The design team is working on the issues and should resubmit soon.
I’ll let you know how the recheck went, once complete.
Thanks,
Michael T. Helmer
Senior Building Plans Examiner
Development Services DepartmentBuilding Division
Working together to build a quality community.
Civic Center | 311 Vernon Street | Roseville, CA | 95678
-
PASS Program Introductory Webinar
- Check out our new webinar outlining the PASS Program! Share this:EmailFacebookTwitter
Check out our new webinar outlining the PASS Program!